总投资6亿,烟台港拟新建2个5万吨级煤炭接卸泊位

烟台港栾家口港区煤炭作业区1#、2#泊位工程拟启动建设,项目由中兴电力蓬莱发电有限公司负责建设与运营,总投资61037万元,计划施工期约12个月。目前项目工程生态环境影响报告书已编制完成,正处于报批前公示阶段,拟向生态环境主管部门报批。

图片

该工程选址于烟台市蓬莱区西北海域、栾家口港区西侧,依托在建西防波堤工程北段西侧直立段既有沉箱基础,新建1#(南侧长230m)、2#(北侧长260m)两个5万吨级专业化煤炭接卸泊位,码头岸线总长490m,单个泊位年通过能力440万吨,合计年设计通过能力达880万吨(先期安排年吞吐量685万吨)。配套港池将疏浚停泊水域(设计底高程-15.1m)及直径400m的回旋水域(设计底高程-14.4m),总疏浚量约129.81万立方米。

在作业工艺与绿色集疏运方面,码头上部拟配置4台额定能力1500t/h的桥式抓斗卸船机(预留远程控制接口),并实行“码头不设堆场”的直输模式:电煤卸船后经双路带式输送机(额定能力3000t/h)汇总至T0转运站,再通过沿西防波堤架设的约2.3公里全封闭管带机廊道,直达后方中兴电力蓬莱一期2×100万千瓦超超临界燃煤电厂圆形煤场,实现大宗散货从船舱到电厂的全封闭、零外排绿色集疏运。

项目建成投产后,将全面满足后方临港电力工业的燃料调入需求,进一步优化烟台港能源运输通道与大宗散货绿色集疏运格局。

English

The total investment is 600 million yuan, and Yantai Port plans to build two 50000 ton coal unloading berths

The construction of berths 1 and 2 in the coal operation area of Luanjiakou Port in Yantai Port is planned to start. The project will be constructed and operated by Zhongxing Power Penglai Power Generation Co., Ltd. with a total investment of 610.37 million yuan and a planned construction period of about 12 months。Current project ecological environment impact reportbookThe preparation has been completed and is currently in the stage of public announcement before approval. It is planned to be submitted to the ecological environment regulatory department for approval。

图片

The project is located in the northwest sea area of Penglai District, Yantai City, on the west side of Luanjiakou Port Area. It relies on the existing caisson foundation on the west side of the northern section of the under construction West Breakwater Project, and will build two 50000 ton specialized coal unloading berths, 1 # (230m long on the south side) and 2 # (260m long on the north side). The total length of the dock shoreline is 490m, and the annual throughput capacity of a single berth is 4.4 million tons. The total annual designed throughput capacity is 8.8 million tons (with an initial planned annual throughput of 6.85 million tons). The supporting harbor will dredge the berthing water area (design bottom elevation -15.1m) and the 400m diameter swirling water area (design bottom elevation -14.4m), with a total dredging volume of approximately 1.2981 million cubic meters.

In terms of operation technology and green collection and distribution, it is proposed to equip the upper part of the dock with four bridge type grab bucket unloaders with a rated capacity of 1500t/h (with remote control interfaces reserved), and implement a direct transportation mode of "no yard at the dock": after unloading the coal, it will be collected by a double belt conveyor (rated capacity of 3000t/h) to the T0 transfer station, and then transported directly to the circular coal yard of Zhongxing Power Penglai Phase I 2 × 1 million kW ultra supercritical coal-fired power plant through a 2.3-kilometer fully enclosed pipe belt conveyor corridor erected along the west breakwater, achieving fully enclosed and zero discharge green collection and distribution of bulk cargo from the cabin to the power plant。

After the project is completed and put into operation, it will fully meet the fuel transfer demand of the power industry in the rear port area, further optimizing the energy transportation channel and green bulk cargo collection and distribution pattern of Yantai Port。